Thursday, 10 November 2022

Namibia: Second Phase of Namibia Airport Road Construction Project

Second Phase of Namibia Airport Road Construction Project Commenced in June 2022 in Windhoek

Construction works on the road between Windhoek and Hosea Kutako International Airport is underway.

The second phase, or Phase 2B, of the new airport road project to upgrade the road between Windhoek and Hosea Kutako International Airport (HKIA) has begun. The project is being financed by a grant of more than N1.035 billion (US$69.5 million) from the Chinese government.

The project's construction contractor is Zhong Mei Engineering Group, with VKE Namibia Consulting Engineers as consultants. The Roads Authority is supervising the project.

Zhong Mei Engineering Group is a Namibian-registered Chinese-owned engineering services company.

VKE Namibia, part of the SMEC Group, offers engineering consulting and project management services in Namibia.

Phase 1 of the project started from the Sam Nujoma interchange (on the existing Western Bypass), went east past the University of Namibia, the Auas interchange and the Robert Mugabe interchange and ended near the Old Age Home in Auasblick. This phase was 10 kilometres and was fully funded by the Namibian government.

Phase 2A consisted of a road continuing from the Old Age Home, following an easterly direction up to the Dordabis interchange, a distance of 19.5 kilometres.

At the ground-breaking ceremony earlier in May, John Mutorwa, Minister of Works and Transport said the new phase of the project (Phase 2B) included the construction of the third and last section of the road which would be a dual carriageway. That phase will begin at the Dordabis interchange and continue towards the HKIA and cover 21 kilometres. 

“I have been informed that the scope of works of this phase includes the construction of 21.3 kilometres of dual carriage freeway, three interchanges two river bridges and drainage structures,” the minister said.

Mutorwa emphasized the opportunities from the project in supplying and subcontracting specialized works to local small and medium enterprises (SMEs) and subcontractors. The road represents a positive investment in the country and will contribute to socio-economic growth and serve future generations.

President Hage G. Geingob undertook today an inspection of progress made on one of the key infrastructure projects in the country, the Windhoek-Hosea Kutako International Airport Road. The highway, which will ease congestion to the Airport is on track for completion in 2024.

“Furthermore, local subcontractors on the project will be exposed to technological advancements through skills transfer which results in positive economic growth for the nation,” Mutorwa said. He also confirmed the creation of 270 jobs for Namibians during the construction phase of the project.

Roads Authority CEO, Conrad Lutombi confirmed that the project would be completed by September 2024. It is part of the Harambee Prosperity Plan II and is also per the fifth National Developmental Plan (NDP5). The completed road would boost economic growth by allowing quicker movement to and from Windhoek. “The dual carriageway will also improve our links to the new SADC Gateway Port at Walvis Bay,” Lutombi said.

Purchase photo/4K video: portfolio1 portfolio2
Aerial photo/video service/inquiries: info@traveltonamibia.com
Telegram: ExploringNamibia

Wednesday, 2 November 2022

Namibia: Second Phase of Airport Road Project

Namibia: Second Phase of Airport Road Project Started in May 2022

WORK on the second phase of a project to upgrade the road between Windhoek and Hosea Kutako International Airport (HKIA) has started in May.

The second phase of the project is financed through a grant of more than N$1 billion from the Chinese government.

The contractor is Zhong Mei Engineering Group, which is a Namibian-registered Chinese-owned company, and the consultant is VKE Namibia Consulting Engineers under the supervision of the Roads Authority.

Speaking at the groundbreaking ceremony for the new phase of the project on Tuesday, minister of works and transport John Mutorwa said the phase involves the construction of the third and last section of the road as a dual carriageway.

Mutorwa said this phase starts at the Dordabis interchange and continues towards the HKIA, covering a distance of about 22 km.

"I have been informed that the scope of works of this phase includes the construction of 21,3 kilometres of dual carriage freeway, three interchanges two river bridges and drainage structures," the minister said.

He said the project would provide ample opportunity for supplying and subcontracting specialised works to local small and medium enterprises and subcontractors.

Mutorwa said the road was a huge investment which would significantly contribute to the socio-economic growth of the country and would serve many generations to come.

"Furthermore, local subcontractors on the project will be exposed to technological advancements through skills transfer which may result in positive economic growth for the nation as a whole," Mutorwa said.

He said he had been informed of 270 jobs which would be created for Namibians during the construction period of this phase.

Roads Authority chief executive officer Conrad Lutombi this week said the construction is expected to be completed by September 2024.

Wednesday, 26 October 2016

Namibia: Hosea Kutako International Airport safety notice

#WindhoekAirport
#HKIA
#NOTAM
#WindhoekHoseaKutakoInternationalAirport
 
Hosea Kutako International Airport (HKIA) had to issue a Notice to Airmen (NOTAM) earlier on 26 October due to a safety hazard as there was a disabled aircraft at Threshold 26. At least one flight was unable to land and had to return to Johannesburg. The NOTAM was issued at 14:40 and was lifted at 15:20 and the airport is fully operational again. A NOTAM is a notice filed with an aviation authority to alert aircraft pilots of potential hazards along a flight route or at a location that could affect the safety of the flight. It could not be confirmed how many planes were unable to land.